Project Detail
13.5 MW, Run-of-River, estimated to be commissioned in 2017. Annual production of 92 GWh The head is 39 m and the discharge is 43 m3/s.
Sluicer
Solution: SediCon proposed a combined solution of SediCon Gravel Excluder and SediCon Sluicer. One Ø355 SediCon Sluicer was installed together with a Stafsjø knife gate valve, DN300. The Gravel Excluder will remove rocks from the intake and the SediCon Sluicer will remove finer sediments inside the tunnel. In addition, a monitoring system consisting of pressure cells and piezometers was installed to monitor the sediment levels.
Implementation: The installation started in October 2016 and was completed in January 2017.
Results: The SediCon Sluicer is estimated to remove 200 m3 of sand per hour.
Gravel Excluder
Solution: SediCon proposed a combined solution of SediCon Gravel Excluder and SediCon Sluicer. One Ø630 SediCon Gravel Excluder was installed together with a Stafsjø knife gate Valve, DN600. The Gravel Excluder will remove rocks from the intake and the SediCon Sluicer will remove finer sediments inside the tunnel. In addition, a monitoring system consisting of pressure cells and piezometers was installed to monitor the sediment levels.
Implementation: The installation started in October 2016 and was completed in January 2017.
Results: The SediCon Gravel Excluder is estimated to remove 300m3 of sand per hour